The table contains information provided by a company.
- budgeted direct labour hours – 8,000
- actual direct labour hours worked – 7,500
- budgeted overhead expenditure – £104,000
- actual overhead expenditure – £112,500
What is the amount of the overhead over / under recovery?
Select ONE answer:
- £7,500 under-recovered
- £8,500 over-recovered
- £8,500 under-recovered
- £15,000 under-recovered
Show your workings to arrive at your answer, and explain and justify your reasons:
……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………
This multiple-choice question is suitable for Accounting KS5 classes.
The answer is 4
- Not correct
- Not correct
- Not correct
- Correct – £112,500 – £104,00 + ((£104,000 / 8,000) * (8,000 – 7,500))