ISA (UK) 315 states that an internal control system in an organisation consists of five components:
- the control environment
- the entity’s risk assessment process
- the information system
- the control activities
- the monitoring of controls
For each of the following examples, select the component which it illustrates:
- Review of actual performance against the budget
Select ONE answer:
- the control environment
- the control activities
- the entity’s risk assessment process
- the monitoring of controls
Show your workings to arrive at your answer, and explain and justify your reasons:
……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………
This multiple-choice question is suitable for Accounting KS5 classes.
The answer is 2
- Not correct
- Correct => Review of actual performance versus budget is a control activity.
- Not correct
- Not correct