A company makes three products for which the following details are given.
product P £ product Q £ product R £
selling price per unit 20 24 36
direct material per unit 9 12 15
direct labour per unit 5 3 9
The same material is used by all three products and it costs $3.00 per kilo.
There is a shortage of material.
In which order of priority listed below should the products be made in order to achieve maximum profit from the available material?
Select ONE answer:

Show your workings to arrive at your answer, and explain and justify your reasons:
……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………
This multiple-choice question is suitable for Accounting KS5 classes.
The answer is 4
- Not correct
- Not correct
- Not correct
- Correct – Correct – CM R = £12, CM Q = £9, CM P = £6