The standard time for a job is set at 50 hours. The standard direct labour rate is £8.00 per hour.

The job was completed in 65 hours at a direct labour cost of £455.

What is the direct labour rate variance?

Select ONE answer:

  1. £55 adverse
  2. £55 favourable
  3. £65 adverse
  4. £65 favourable 

Show your workings to arrive at your answer, and explain and justify your reasons:

……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………

This multiple-choice question is suitable for Accounting KS5 classes.

The answer is 4

  1. Not correct
  2. Not correct
  3. Not correct
  4. Correct – £455 / 65 = £7 ==> £8 – £7 * 65 hours = £65 FAV

Creative Commons License
This work is licensed under a Creative Commons Attribution 4.0 International License.

Author: stuart001uk2014

Referral marketing, business, economics and accounting s​pecialist & corporate mentor

Leave a Reply

Please log in using one of these methods to post your comment:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: