
The following information relates to labour costs.
- standard pay rate per hour — £7.50
- actual pay rate per hour — £9.00
- actual hours worked — 60,000 hours
- labour efficiency variance — £12,000 adverse
What is the standard number of labour hours for actual output?
Select ONE answer:
- 48,667
- 51,333
- 58,400
- 61,600
Show your workings to arrive at your answer, and explain and justify your reasons:
……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………
This multiple-choice question is suitable for Accounting KS5 classes.
The answer is 3
- Not correct
- Not correct
- Correct ==> (60,000 – X) * £7.50 = £12,000 Adverse where X = 58,400
- Not correct
This work is licensed under a Creative Commons Attribution 4.0 International License.