A company uses a machine hour basis to absorb its overheads.
The following information is provided for its last period.
actual budgeted
- overheads £299,000 £350,000
- machine hours 46,000 50,000
Which statement regarding overheads is correct?
Select ONE answer:
- They were over absorbed by £23,000.
- They were under absorbed by £23,000.
- They were over absorbed by £51,000.
- They were under absorbed by £51,000.
Show your workings to arrive at your answer, and explain and justify your reasons:
……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………
This multiple-choice question is suitable for Accounting KS5 classes.
The answer is 1
- Correct ==> £350,000 / 50,000 hours = £7 * 46,000 hours = £322,000 – £299,000 = £23,000
- Not correct
- Not correct
- Not correct
This work is licensed under a Creative Commons Attribution 4.0 International License.