The standard cost of materials for production amounts to £17,100.
The materials price variance is £1,800 favourable, the materials usage variance is £1,000 adverse.
What is the actual material cost?
Select ONE answer:
- £14,300
- £15,300
- £16,100
- £16,300
Show your workings to arrive at your answer, and explain and justify your reasons:
……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………
This multiple-choice question is suitable for Accounting KS5 classes.
The answer is 4
- Not correct
- Not correct
- Not correct
- Correct == > £17,100 – £1,800 + £1,000