A manufacturing business has provided the following information.
- budgeted labour hours 12 000
- budgeted overhead absorption rate £7.50 per labour hour
- actual overhead cost £101 250
- actual labour hours 15 000
What is the over or under absorption of overheads?
Select ONE answer:
- £11 250 under absorbed
- £11 250 over absorbed
- £20 250 under absorbed
- £20 250 over absorbed
Show your workings to arrive at your answer, and explain and justify your reasons:
……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………
This multiple-choice question is suitable for Accounting KS5 classes.
The answer is 2
- Not correct
- Correct
- Not correct
- Not correct
This work is licensed under a Creative Commons Attribution 4.0 International License.